Kenya cabinet approves KAA financing packages

KIBAKI’S INFRASTRUCTURE LEGACY SECURE AS CABINET APPROVES AIRPORT FINANCING

The aviation sector in Kenya, and in fact in the wider region, will be jubilant as news emerge from Nairobi that the last cabinet meeting chaired by President Kibaki has approved the financing proposals by the Kenya Airport Authority, for the pending Project Greenfield which includes the building of a second runway, but also the subsequent modernization and refurbishment of the present terminals one to three.

Though repeatedly mentioned here, the various components of the ongoing works at Jomo Kenyatta International Airport and the planned expansion, are worth summarizing here once again for the benefit of readers:

· Project Greenfield – set to catapult Kenya’s aviation industry into the 21st century with a new mega terminal to be primarily used by national airline Kenya Airways and its alliance partners. The tender awards have been concluded and the remaining financing package is currently being finalized with Chinese state owned banks used to facilitate major contracts of this nature. Groundbreaking is expected to take place next year and construction is likely to kick off proper by November 2013 with a completion date for the terminal by 2017. Cost of this component is at current prices about 55 billion KShs. The second runway, which is part of this project, will see construction start in 2013 too, is expected to last about 3 years and estimated at just under 13 billion Kshs.

· Terminal Four – This ongoing construction which started in Q3 of 2010, will probably be completed in late 2013 but delays are reported on sourcing and tendering of equipment and furnishings which may delay opening into early 2014. This new terminal will cost just under 10 billion KShs when complete and cater for an increase in passengers until Project Greenfield will come on line, in addition of which it will allow for the start of work on the present terminal building which was opened in 1978 and is now processing nearly 3 times the initial capacity.

· Terminal 1 – 3 Renovations – This project will only start when Terminal Four is fully operational and then be carried out in phases, at an estimated cost of around 8 billion KShs at current prices.

In order to finance these ambitious projects KAA has in July this year doubled the passenger tax for international departures from 20 to 40 US Dollars and the expected increase in flights and passenger numbers is according to a source close to KAA the repayment of loans viable, leaving sufficient cash flow at hand for recurrent and further investment expenditure in coming years. For 2012 over 7 million passengers are expected to fly in, through and out of Nairobi’s JKIA and passenger growth for the next few years is expected to be in the 10 -15 percent range, making the timely completion of all pending projects an absolute must, if Kenya Airways’ ambitious expansion plans, set to double their fleet by 2016, is to materialize. Watch this space.